What is SAP MM ? Features and Benefits of SAP MM


MM Stands for Material Management.It is one of the largest functional module in SAP. This module mainly deals with the Procurement Process, Master Data (Material & Vendor Master), Inventory Management, Valuation of Material & Account Determination, Material Requirement Planning, Invoice Verification etc.

Logistics is the most extensive area of the SAP Application and contains the largest number of components as follows..
MM : Material Management
PP : Production Planning
PM : Plant Maintenance
PS : Project Systems
QM : Quality Management
SD : Sales and Distribution
Above of this, SAP MM is the key area within Logistics in SAP. It is very important component of Logistics because it is tightly integrated with all of other components of SAP Logistics. MM contains of the following components..

MM-PUR : Purchasing
MM-IM : Inventory Management
MM-CBP : Consumption based Planning
MM-IV : Invoice Verification
MM-EDI : Electronic Data Inter-exchange
MM-IS : Information System


Material Management is the module that supports the procurement activities in an organization right 
from the planning and purchasing to inventory management and quality control. This module has several features and functionality that are fully integrated with the other important modules like Finance and Control, Sales and Distribution, Production Plannin 

The procurement process consists of a chain of events that take place in order. Starting from the creation of a Purchase Requisition (PR), it moves to the authorization of PR and creation of a Purchase Order (PO). Subsequently, the Goods Receipt (GR) is generated on receipt of the goods ordered, Invoice Verification takes place and the Quality Control activities are set in motion. Thereafter, the payment is sent to the vendors for their goods /services.

Benefits of SAP MM

Customer demands are changing rapidly, an organization’s efficiency is measured primarily by its ability to cater to the market demands in the shortest time possible. For this to happen, the business has to have stock of the required raw materials at the right time and must be able to use it efficiently A proper Material Management process ensures that there is never a shortage of materials or any gaps in the supply chain process of the organization. The SAP MM automates the procurement and material management activities to make the processes smoother and effective. Some prominent benefits of SAP MM are:
  • Reduces material costs by avoiding stocking of unnecessary or obsolete materials
  • Inventory losses are minimized
  • Direct labour costs are reduced and labour can be used efficiently
  • Manufacturing cycle times are reduced and can be controlled effectively
  • Effective inventory management and reduces expenditure on unwanted material storage
  • Improves delivery time and increases transparency across the organization

 

Monday, October 5, 2015

SAP PM Preventive Maintenance Scheduling - Strategy Plan

About Strategy Plan :


The strategy plan incorporates where  maintenance activity based on each other or supersede each other.The ability to vary the inter­vals as well as the task list operation application based on intervals.


 Process Flow (Time Based Strategy Plan)



PM Time Based Strategy Plan


Step 1 : Create Strategy - IP11


SAP PM Create Strategy

Tolerance Limit SAP

Call Horizon :
Call horizon is used to propose a pre call date for the maintenance plan. for example if the maintenance plan is for every 1 month and you need to release the call say 3 days before , then you specify the call horizon as 90 % and hence it will release the call on 27th day. For releasing the call you have either run IP10 manually or IP30 regularly.

Tolerance and Shift Factor :
 When the preventive maintenance order is completed outside of the shift tolerance limits, the shift factor determines the adjustment to be made on calculating the next planned date. Example, an order was completed 15 days late outside of 10% tolerance with shift factor 50%  the next plan date is delayed 7.5 days. 


Maintenance Packages


PM Maintenance Package
SAP PM Package Sequence





Step 2 : Create General Maintenance Task List - IA05


PM General Maintenance Task List

PM Task List


SAP Task List Operation



Maintenance Package






   Step 3 : Create Strategy Plan - IP42

PM Maintenance Plan









SAP PM Scheduling Period


 



  


Step 4 : Schedule Maintenance Plan : IP10

Maintenance Plant Scheduling

Schedule Maintenance Start Cycle

Strategy Plan Package

SAP PM Maintenance Package Sequence





Save :







Deadline Monitoring : IP30




Maintenance Order will generate automatically.

Now Check by IW38


Its showing two Maintenance Order has been generated through maintenance plan.

Also Can check by IP10


Its showing two schedule has been called and created preventive maintenance order and next maintenance plan date is 30.12.2015