SAP PM Preventive Maintenance Scheduling - Strategy Plan

About Strategy Plan :


The strategy plan incorporates where  maintenance activity based on each other or supersede each other.The ability to vary the inter­vals as well as the task list operation application based on intervals.


 Process Flow (Time Based Strategy Plan)



PM Time Based Strategy Plan


Step 1 : Create Strategy - IP11


SAP PM Create Strategy

Tolerance Limit SAP

Call Horizon :
Call horizon is used to propose a pre call date for the maintenance plan. for example if the maintenance plan is for every 1 month and you need to release the call say 3 days before , then you specify the call horizon as 90 % and hence it will release the call on 27th day. For releasing the call you have either run IP10 manually or IP30 regularly.

Tolerance and Shift Factor :
 When the preventive maintenance order is completed outside of the shift tolerance limits, the shift factor determines the adjustment to be made on calculating the next planned date. Example, an order was completed 15 days late outside of 10% tolerance with shift factor 50%  the next plan date is delayed 7.5 days. 


Maintenance Packages


PM Maintenance Package
SAP PM Package Sequence





Step 2 : Create General Maintenance Task List - IA05


PM General Maintenance Task List

PM Task List


SAP Task List Operation



Maintenance Package






   Step 3 : Create Strategy Plan - IP42

PM Maintenance Plan









SAP PM Scheduling Period


 



  


Step 4 : Schedule Maintenance Plan : IP10

Maintenance Plant Scheduling

Schedule Maintenance Start Cycle

Strategy Plan Package

SAP PM Maintenance Package Sequence





Save :







Deadline Monitoring : IP30




Maintenance Order will generate automatically.

Now Check by IW38


Its showing two Maintenance Order has been generated through maintenance plan.

Also Can check by IP10


Its showing two schedule has been called and created preventive maintenance order and next maintenance plan date is 30.12.2015



6 comments:

  1. HI Shirazul,
    first of all thanks for the descriptive explanation. I have one question in selecting package. as per your screen shot, you have selection (01.10.2015) you have selected the off state date of 1M and 2M instead of 1M. May i know why..?
    Can't we select the first package as 1M cycle..?
    May be it's a silly question but it will be great if you can clear my doubt.

    Regards,
    Santosh

    ReplyDelete
  2. Dear Santosh Verma,

    Your Observation is correct. I forgot this things why I have select 2M for that time.There may be some date related issue (may be i run the process in back date)but I think it will not create more confusion for learners,because it is just an example. Thanks for your reply

    Shirazul

    ReplyDelete
  3. nice article very useful and informative sap mm training

    ReplyDelete
  4. Interesting Content Thanks For Sharing.
    Please do visit the link below.
    customized inventory software services in bangaore

    ReplyDelete
  5. Preventive Maintanance attempts to help you proactively perform maintenance, repairs, and replacements so that you can prevent failures before they ever have the chance to occur.


    Preventive maintanance plan
    Agaram infotech

    ReplyDelete
  6. There is a lot of information in your article. The information provided was of a high standard. Please continue to give us such good information. I just published a related article Click Test Check your CPS now!. See my latest article Click Speed Test – Check Clicks Per Second. Please visit my article and let me know what you think.

    ReplyDelete