Business Process Overview :

Preventive maintenance is the pre-planned maintenance activity that performed while the equipment is still working, so that it does not break down unexpectedly. Preventative maintenance is planned so that any required resources are available.

Preventive Maintenance is also used to avoid system failure other objects, which - in addition to the repair costs - often result in much higher costs subsequently owing to production breakdown.

There are many benefits in using preventive maintenance within your company. It is the generic term for systematic inspections, detection, Correction for which the time and scope of the work can be planned in advance.

You can use maintenance plans to describe dates and the extent of preventive and inspection maintenance tasks which can be planned for technical objects. You can ensure that your technical objects are always maintained on time and in this way, ensure that they function optimally.

Preventive Maintenance :Types

Preventive Maintenance Types
 Time Based Preventive Maintenance : 

In time-based preventive maintenance, the maintenance tasks are planned and performed depending on the time-dependent intervals determined. Example : There are vehicles(equipment) which needs to be serviced after different-2 cycles like1 month, 4 months, 6 months, 12 months..etc

 Performance Based Preventive Maintenance : 

In Performance Based preventive maintenance performed based on Counter Reading. Example :  There are vehicle which needs to be serviced after running 5000 kms, 10000 kms and so on.

Condition Based Preventive Maintenance :  

In the case of condition-based maintenance, maintenance activities are always performed when the measuring point of a technical object has reached a particular state or outside a specific value range. For example, a thread depth below 15 mm or temperature higher than 85 C.
 
Strategy and Task List

Maintenance Strategy consist of several maintenance packages. It is the scheduling rule for preventive maintenance.


Maintenance task lists describe a sequence of individual maintenance activities which must be repeatedly performed within a company. Task lists eventually become the operations within the maintenance order that is generated through the Maintenance Plan.

There are three types of task lists that can be distinguished from one another using indicators:

Configuration Steps : 

Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Basic Settings > Define Plant Sections


Plant Section SAP PM

Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Basic Settings > Define Maintenance Planner Groups


Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Basic Settings > Define ABC Indicators




Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Maintenance Plans > Set Maintenance Plan Categories

SAP Maintenance Plan Catagories


Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Maintenance Plans > Define Number Ranges for Maintenance Plans

Maintenance Plan Number Range

Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Maintenance Plans > Define Number Ranges for Maintenance Items


Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Maintenance Plans > Define Sort Fields for Maintenance Plan

Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Task Lists > General Data > Maintain Task List Status


Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Task Lists > Control Data > Define Number Ranges for General Maintenance Task Lists

General Maintenance Task List Number Range

Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Task Lists > Define Number Ranges for Equipment Task Lists



Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Task Lists > Define Number Ranges for Task Lists for Functional Locations



Plant Maintenance and Customer Service > Maintenance Plans, Work Centers, Task Lists and PRTs > Task Lists > Control Data > Define Profiles with Default Values

End

Tuesday, September 22, 2015

SAP PM Measuring Point, Counter and Measurement Document Configuration and Process

Overview : 
Documenting the condition of a particular object (Equipment) is of great importance in cases where detailed records regarding the correct condition have to be kept for legal reasons. This could Involve critical values recorded for Machine or  environmental protection purposes, hazardous working areas that are monitored for health and safety reasons, the condition of equipment in hospitals (intensive care units), as well as measurements of emissions and pollution for objects of all types
 
Measuring Point :
 In SAP System Measuring points describe the physical locations at which a condition is described , ( For example, Temperature,  Pressure on a Boiler, Dash Board or  Odometer of a Vehicle The characteristics associated with the measuring points which record the value can only be numeric characteristic.


 Measuring points are located on technical objects, in other words, on pieces of equipment or functional locations. For every measuring point there should be some characteristics to measure the reading.

Purpose :
For better monitoring of capacity utilization, maintenance objects have measuring points and counters to record flow quantities or operating hours, for instance. Measurement and counter readings are stored in the system in the form of measurement documents.  These documents are the basis for performance-based maintenance planning.

Counter :

Counter is type of measuring point, where a continuous reading is recorded (e.g. Kilometer, Hour Meter). Counter readings are taken at counters at particular intervals and in particular measurement units. 

The above Picture given (Kilometer) is treat as a counter where Kilometer reading we can take from certain intervals.



Characteristics and Class :

Characteristics : Specification or Quality belonging to a Technical Object (  Equipment, Functional Location )Characteristics are used to store additional data or condition value.

Class : A Class is a collection of Characteristics. Class is assign to Equipment or Functional Location


Step 1 : Create Characteristics ( T Code : CT04)




Step 2 : Create Class ( T Code : CL02)


SAP Create Class



Create Class SAP PM


Step 3 : Assign Class to Equipment 






 Step 4 : Create Measuring Point - IK01 (Counter Base)


SAP PM Measuring Point Counter



Step 5 : Create Measurement Document  ( T Code : IK11)


PM Measurement Document IK11

 Enter

PM Measurement Document

 Save

Step 6 :Measurement  Document List : IK17

SAP PM Measurement Document List





Configuration : 

Define measuring points category 
IMG>Plant maintenance & customers services>Master data in plant maintenance & customers services>Basic setting>Measuring point counter & measuring documents>Define measuring point category. 



Click on new entry and create new measuring point category if required

Create no of ranges for measuring point 
IMG>Plant maintenance & customers services>Master data in plant maintenance & customers services>Basic setting>Measuring point counter & measuring documents>Create no ranges for measuring point.


Click on intervals & create no ranges

Create no of ranges for measuring Documents

IMG>Plant maintenance & customers services>Master data in plant maintenance & customers services>Basic setting>Measuring point counter & measuring documents>Create no ranges for measuring documents


Define field selection for measuring point & measuring Documents

IMG>Plant maintenance & customers services>Master data in plant maintenance & customers services>Basic setting>Measuring point counter & measuring documents>Define field selection for measuring point & measuring Documents (T Code : OIMRC)


 

END
 

Tuesday, August 12, 2014

SAP MM - FI Period Open and Close Error and Solve - Message no. M7053 and F5286

T Code : MMPV - Close Period ( For Error  Massage M7053)
In MMPV you can execute period closing up to the end of the current fiscal year. The period closing program updates the administration record, thus ensuring that the stock data of the material master are updated.
If, for example, you want to close your periods up to 10/2014, you are not allowed to post values in 08/2014. Therefore, if you still want to make postings in period , you should execute period closing only for a maximum of t+1 periods.


Then Execute



MMRV - Allow posting to previous period. (You Can Check the Present Open Period , but don't make any Change)
This transaction allows you to view current period and change setting for posting to previous period.



OB52 - Change view "Posting Periods: Specify Time Intervals" ( For Massage F5286 )
(Need to Change period while showing this Error)

OB52

Solve by OB52 (Update Required Period , Its can generate Transport Request)

Posting Periods

Then SAVE. Error will Solve.

Friday, May 2, 2014

Unprocessed future change recs for order " " prevent del. flag/completion massage no. CO688 Error

Unprocessed future change recs for order " " prevent del. flag/completion massage no. CO688 Error Solving Process.

This Error showing while make to Order Business Completion after TECO.


Solving Process..

 Click on Reprocessing incorrect goods movements. Set The Plant and Order like below screen and
Execute




Select the line and Delete.


Then Save.

Now order will make Business Completed (CLSD)

Also you may have run the following transaction to identify errors: 

COGI - For post processing goods movements 
CO1P - Predefined Confirmation Process
IW46 -  For post processing confirmations from CATS
COFC - For post processing actual costs
COGI - For post processing goods movements

If Settlement Required then do it by KO88 for required period.